Aboriginal Agreements

Northern Flood Agreement

Table of Contents

Schedule "G"

  1. The following items of work are intended to be completed by Cross Lake residents for the following stipulated amounts:
    Item of Work Total Balance to Complete by Native Band
    Water Supply
    $50,000
    $34,000
    Building Relocation
    300,000
    290,000
    Roads
    350,000
    270,000
    Walkways
    150,000
    150,000
    Shoreline Protection
    150,000
    150,000
    Dock Improvement
    250,000
    169,000
    Totals:
    $1,250,000
    $1,063,000
  2. The following items of work are intended to be completed by Nelson House residents for the following stipulated amounts:
    Item of Work Manitoba Hydro and/or Others Balance to Complete by Native Band
    Slope Protection  
    $632,000
    Beach  
    30,000
    Docks
    $80,000
    15,000
    Water Intakes (includes new pumphouse)
    90,000
    10,000
    Notigi and Wapisu Landing
    Facilities and Docks  
    100,000
    Burntwood Portages
    Downstream Notigi  
    25,000
    Totals:
    $170,000
    $812,000
    Total for Items 1 & 2  
    $1,875,000
    (This is in addition to the Clearing Contract awarded to Nelson House Band of approximately $1,000,000)